Thursday, October 4, 2012
CONSTRUCTION UPDATE/CLOSING
1. We will be closed the entire day of Oct 17 as we have confirmation that ComEd will be switching our electrical service.
2. Please plan on working your regular schedule that week except for the 17th.
3. Currently the new parking lot asphalt is being laid and within the next couple of weeks, when this is completed, we will be relocating the patron entrance door and parking lot to the west side. More details and solid dates will be forthcoming. We will have library entrance signs created to help direct patrons.
4. A construction meeting is being held next Monday and we will have a timeline and more details for the phasing process.
5. When Phase 2 construction begins, staff will no longer have to park in Woodbine as a construction fence will encompass the front area of the addition.
6. Please continue to use Woodbine until I send you an official email providing the exact date for the switch.
Thanks for being a great team. After Monday’s meeting I hope to give you more details. Questions – come see me or Sara.